What are the preparations before installation?
2022.Dec 06

Photovoltaic Construction Guide

Part 1: What are the preparations before installation?


Photovoltaic has gradually penetrated into everyone's life, especially after experiencing the power cut storm some time ago, many friends have privately messaged me, wanting to know how to build a household photovoltaic power station? So today is the most complete construction guide on the entire network, and I will explain it to everyone step by step! Friends in need, come and see! The first article is to share with you, if you want to build a household photovoltaic, what preparations should you do in the early stage?

In order to make it easier for everyone to understand, I will list the most frequently asked questions through question and answer, and reply in a targeted manner. If you haven’t answered the question you want to ask, please leave a message in the comment area, and I will reply again. !

If household residents want to install photovoltaic power plants, who should they contact first?

As the first step, it is recommended that you consult the local power grid company to understand the precautions before installation. Why do you suggest that you consult the local power grid company? Because different regions have different requirements and even restrictions, it is impossible to give everyone a unified standard, so it is safest to consult the local power grid company! At the same time, you can also communicate with local photovoltaic equipment dealers to understand the price, way and installation of equipment, etc.

What materials do I need to prepare for grid-connection filing?

Before installing household photovoltaics, we first need to go to the local grid company to fill out the grid connection application form, because the project filing is currently initiated by the grid company instead of the customer. All you need is the following materials:

Applicant's valid identity certificate: Resident ID card (or temporary ID card), household registration booklet, or other valid identity certificates can be selected.

Power station address ownership certificate: including the house ownership certificate, house purchase contract, or land use certificate issued by the competent government department at the township level or above. This point is very important. If this step is missing, it is very likely that your photovoltaic power station will eventually become an illegal building and will be required to be demolished by relevant agencies!

Other materials provided by the local power grid company in accordance with relevant regulations. This point is what I said earlier. Different places have different regulations, but no matter what the regulations are, it is good for everyone to provide relevant materials and go through relevant procedures as required.

Generally speaking, it is relatively simple. Once the materials are ready and the procedures are complete, you can start the next step of grid connection filing. Speaking of this, everyone must not take it lightly. It seems that the grid connection filing seems to be a matter of the power company. There are still many details that need our attention! 